All systems are operational

About This Site

Maintenances and incidents regarding our services, networks and datacenters can be followed here.

Scheduled Maintenance
[DC3] - Switch Maintenance - Room 4-3 Rack E21

We will need to replace the switch in DC3 Room 4-3 Rack E21

The replacement will last about 15min.

Servers will be rebooted on our side to populate the DHCP snooping database.

During this time, all the servers won't be reachable over the public network

Start : 23-Jul-2019 0800Z 1000LT

Duration : 15 minutes

Preventive maintenance due to current heatwave

On 24th & 25th July we will reach record highs, with 42°C being the highest recorded temperature in the last 20 years.
This will be a challenge for our equipment and teams, but everyone is mobilized, and exceptional means have been put in place to keep everything up and running.

This status has been created preemptively and will be updated on July 24th as needed.

Risk evaluation per DC : DC2 High DC3 Very High DC4 No risk DC5 Low risk

[Paris core router bb1.dc3] Router upgrade

Location : Paris - core router bb1.dc3

We are planning to upgrade the router firmware to the latest recommended by Cisco. The maintenance will be done in 2 steps to prepare the upgrade and then to apply.

Impact : This might lead to rerouting / latencies during the maintenance window. All Paris DCs are impacted.

Preparation : 30-Jul-2019 0400Z (0600LT) - duration 2h
Full upgrade : 31-Jul-2019 0200Z (0400LT) - duration 5h

UPDATE: Maintenance was planned for the 23th and 24th, due to high temperatures, we are changing the dates for the 30th and 31st.

TGBT C – DRC control relays replacement

Following a fault on TGBT C DRC control observed on June 12 and the fault identification on June 18 we will replace the PLC control relays and carry out a load test to confirm the installation is fully operational.

impacts: This intervention does not present any particular risk of service interruption and will be processed on worked hours.

Start : 19-August-2019 1200Z (1400LT)

Duration: 4 hours

DC3 - Semi-Annual Refrigeration Units Maintenance

We will carry out the semi-annual maintenance of the refrigeration units.

No impact is expected.

Start : 23-Aug-2019 0600Z 0800LT

End : 03-Sept-2019 1530Z 1730LT

Past Incidents

Saturday 5th January 2019

No incidents reported

Friday 4th January 2019

No incidents reported

Thursday 3rd January 2019

DC3 Network [NETWORK] DC3 - Room 4-4 - Racks C13, C14, C15

We have lost connectivity in DC3 Room 4-4 rack C13, C14, C15

We have already launched actions to fix this as soon as possible

===================

03/01/19 1414Z (1514LT)

All three racks are now reachable. The issue is fixed

Wednesday 2nd January 2019

DC3 Network [NETWORK] DC3 - Room 3-2 - Racks B13, B14, B15 - Replacement of hardware

There will be a short outage (less than a minute) in order to replace a hardware part and improve the network on said racks.
It will be done in the upcoming hour (1545Z, 1645LT).

User Accounts API [SCW] API unavailability

We have had an issue regarding API in Paris and Amsterdam. API was unavailable for around 40 minutes, starting around 0900Z (1000LT) Our team managed to find the root cause and resolve it after investigation.

The service is now back online as it should.

Tuesday 1st January 2019

No incidents reported

Monday 31st December 2018

No incidents reported

Sunday 30th December 2018

No incidents reported