Monday 25th March 2019

[DC5] Electrical maintenance - Generators load tests, scheduled 8 months ago

[DC5] Electrical maintenance - Generators load tests

Location : DC5

What is done : Generators load tests

Proactive maintenance. The power will be switched to the generators. The associated risk is very limited so the maintenance will be done during business hours.

Impact : no impact for customer

Start : 26-March-2019 0700Z 0800LT

Duration : 6 hours

Maintenance completed successfully. Closing.