Tuesday 10th September 2019

DC3 - Redundancy test of DC3 electrical generators, scheduled 1 month ago

DC3 electrical generators - Redundancy test of DC3 electrical generators

Location : DC3 What is done : As part of the preventive maintenance of the Datacenter, we will proceed to a redundancy test of the Datacenter infrastructure. The operation consists of simulating a power failure on the MVLBs and validating the electrical load recovery and working on generator for 4 hours. Impact : no impact on client servers

Start : 9-Oct-2019 0700-1400Z 900-1600LT

Duration : 4 hours