Monday 16th December 2019

DC3 Verification of electrical installations

[DATACENTER DC-3] Verification of electrical installations

What is done : As part of the annual checks, we will carry out a verification of electrical installations on all electrical cabinets.

Impact : There is no provision for service interruption.

Start : 18-Nov-2019 0630Z 0830LT
End : 22-Nov-2019 1700Z 1900LT
Start : 10-Dec-2019 0630Z 0830LT
End : 16-Dec-2019 1700Z 1900LT

Duration : 10 days