[DC3] Preventive mechanical maintenance of generators + load tests of generators
Scheduled Maintenance Report for Scaleway
Completed
The scheduled maintenance has been completed.
Posted Jun 01, 2021 - 18:30 CEST
Update
Update: Load tests of generators chain Dand F1, 31/05• Chain F2 : GRF2-1, 31/05 and GRF2-2, 01/06 + load tests of generatorschain F2, 01/06
Posted May 19, 2021 - 12:53 CEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted May 10, 2021 - 08:30 CEST
Scheduled
We’re going to realize the preventive mechanical maintenance of generators.

The maintenance will be performed electrical chain by electrical chain, so that super-rescue generators (chain F1) can recover the load, in the event of an electrical incident coming from the usual network of energy supply.

Maintenance will be carried out according to the following forecast schedule:
• Chain A : GRA1, 10/05 and GRA2, 11/05 + load tests of generators chain A, 11/05
• Chain B : GRB1, 12/05 and GRB2, 17/05 + load tests of generators chain B, 17/05
• Chain C : GRC1, 18/05 and GRC2, 19/05 + load tests of generators chain C, 19/05
• Chain D : GRD1, 20/05 and GRD2, 25/05 + load tests of generators chain D, 25/05
• Chain F1 : GRF1-1, 26/05 and GRF1-2, 27/05+ load tests of generators chain F1, 27/05
• Chain F2 : GRF2-1, 31/05 and GRF2-2, 01/06 + load tests of generators chain F2, 01/06

Every evening, generators on which maintenance has been done will be put back into service and a generators off-load test will be performed. Load tests of at least 30 minutes will be performed after each completed chain.

No generator will remain out of service in absence of the maintenance company.
Posted Apr 06, 2021 - 14:16 CEST
This scheduled maintenance affected: Dedibox - Datacenters (DC3).