[DC5] LT 7.1 Replacement of cards on UPS following a factory recall
Scheduled Maintenance Report for Scaleway
Completed
The scheduled maintenance has been completed.
Posted Jul 10, 2023 - 17:00 CEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 10, 2023 - 14:00 CEST
Scheduled
We are going to replace the electronic cards of some UPS units following a factory recall. These UPS units supply the racks in the IT rooms.
This maintenance requires isolating each UPS (thanks to the maintenance bypass) in order to work on the device.
The operation will therefore take place UPS by UPS and will have no impact on your equipment hosted in our Datacenter: the other UPSs
of the electrical lineup are sized so as to recover the load from the UPS in maintenance.
The operations will be carried out by our maintainer and under our permanent supervision, according to the following provisional
Posted Jun 01, 2023 - 17:04 CEST