[DC5] Modification of the electrical connection of a rack in production - Room 7/C
Scheduled Maintenance Report for Scaleway
Completed
The scheduled maintenance has been completed.
Posted Sep 23, 2022 - 09:00 CEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 19, 2022 - 09:01 CEST
Scheduled
Following the commissioning of a new bar duct, a migration of one of the two electrical channels is required on the servers in production in room 7/C.

Impact: Each rack listed below will be powered by a single channel for approximately 1⁄2 hour per rack.
Room 7 - Bay C1 to C16 - 19/09/2022
Room 7 - Bay C17 to C30 - 20/09/2022
Room 7 - Bay C31 to C45 - 21/09/2022
Room 7 - Bay C46 to C60 - 22/09/2022
Room 7 - Bay C61 to C73 - 23/09/2022
Posted Aug 25, 2022 - 15:00 CEST
This scheduled maintenance affected: Dedibox - Datacenters (DC5).