[DC5] Move of 48V inverter in the Operator room

Scheduled Maintenance Report for Scaleway

Completed

The scheduled maintenance has been completed.
Posted Feb 24, 2022 - 16:00 CET

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 23, 2022 - 09:00 CET

Scheduled

We are going to move the 48 Volt B inverter from operator room 1 to operator room 2. Inverter B supplies, among other things, bays A1 and B1 where the ADVAs are located. All the other equipment is double powered by the inverter but in 230 Volt.

This intervention takes place over two days with re-energization at the end of the day.

- February 23, 2022 at 9 a.m.: Inverter B cut (48 V and 230 V).
Power up scheduled around 4:00 PM CET.
No power interruption expected, with inverter A still supplying the second channel of equipment.

- February 24, 2022 at 9 a.m.: Inverter B cut (48 V and 230 V).
Final re-energization scheduled around 4:00 PM CET.
No power interruption expected, with inverter A still supplying the second channel of equipment.

During the outage, the equipment will only be supplied by a channel which will be corrugated. The risk lies in the active power supply of the equipment.

In the event of an electrical cut in the HV network during the operation, the maintenance in progress will be interrupted to restart the UPS. The load will be powered by the batteries of the active inverter of the electric chain during the maintainer fallback.

The generators will take over the electric charge automatically thereafter.
Posted Feb 10, 2022 - 17:07 CET
This scheduled maintenance affected: Dedibox - Datacenters (DC5).