Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 10, 2022 - 08:00 CET
Scheduled
We are going to proceed with an electrical reconnection on the 48 Volt inverter A in operator room 1. Inverter A supplies, among other things, bays A1 and B1 where the ADVAs are located, these are also supplied by the inverter energy B. All the other equipment in operator room 1 is double-powered by the inverter but at 230 Volt. This intervention takes place over one day with re-energization at the end of the day.
o March 10, 2022 at 8:00 a.m.: shutdown of inverter A (48 V and 230 V). Power up scheduled around 4:00 p.m. No power interruption expected, workshop A still supplying the second channel of equipment.
During the outage, the equipment will only be supplied by a channel which will be corrugated. The risk lies in the active power supply of the equipment.
Posted Mar 07, 2022 - 12:36 CET
This scheduled maintenance affected: Dedibox - Datacenters (DC5).