Status impact color legend
  • Black impact: None
  • Yellow impact: Minor
  • Orange impact: Major
  • Blue impact: Maintenance
[APPLE Silicon] Planned maintenance for Apple Silicon servers in fr-par-1
Scheduled Maintenance Report for Scaleway
Completed
The scheduled maintenance has been completed.
Posted Jan 17, 2025 - 18:00 CET
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 16, 2025 - 08:00 CET
Scheduled
Datacenter maintenance operations have to be carried out on racks hosting M2-L servers.
No user impact expected, although there is a higher risk of power/network loss during the maintenance window.
Date/Time: Maintenance window from Thursday 16/01 8:00am until Friday 17/01 6:00pm.
Posted Jan 13, 2025 - 16:17 CET
This scheduled maintenance affected: Elements - Products (Apple Silicon).