Connection of UPS rooms 1 and 2 to the BMS.
Scheduled Maintenance Report for Scaleway
Completed
The scheduled maintenance has been completed.
Posted Mar 16, 2023 - 11:30 CET
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 16, 2023 - 09:30 CET
Scheduled
As part of our planned work, we are going to connect the BMS of the UPS in technical rooms 1.1; 1.2;2.1 and 2.2. The UPS of these electrical lineups supply the racks in IT rooms 1 and 2.

This maintenance requires isolating each UPS (maintenance bypass) in order to work on the device.
The operation will therefore take place UPS by UPS and will have no impact on your equipment hosted in our Datacenter: the other UPSs in the electrical lineup are sized to take over the load from the UPS undergoing maintenance.

The operations will be carried out by our maintainer and under our permanent supervision, according to the following provisional schedule:

Thursday 16/03/23 Impacted electrical chain
9h30 – 10h00 AM LT 1.1
10h00 – 10h30 AM LT 1.2
10h30 – 11h00 AM LT 2.1
11h00 – 11h30 AM LT 2.2
Posted Mar 09, 2023 - 12:13 CET
This scheduled maintenance affected: Dedibox - Datacenters (DC5).