Impacted services : Power supply of IT chains A and B
We will do the curative maintenance of certain inverters of electrical chains A and B to replace the batteries end of life. The inverters of these electrical chains supply racks of IT halls.
Operations will be performed by our maintainer under our permanent supervision.
UPS impacted : ASI A1 - 160 batteries - 12/04/2021 ASI A3 - 160 batteries - 14/04/2021 ASI B3 - 160 batteries - 15/04/2021
This maintenance requires isolating each UPS in order to intervene on the device. The downtime of an UPS is estimated to take 7 hours.
The operation will be done on one UPS per day and will have no impact on your equipments housed in our Datacenter : the others UPS of the electrical chain are sized to recover the load from the offline UPS.
Posted Mar 16, 2021 - 10:43 CET
This scheduled maintenance affects: Dedibox - Datacenters (DC3).