[DC3] Router upgrade on Room 4-3
Scheduled Maintenance Report for Scaleway
Completed
The scheduled maintenance has been completed.
Posted Apr 14, 2021 - 07:00 CEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 14, 2021 - 05:05 CEST
Scheduled
A scheduled maintenance is planned in part of the room 4-3, DC3, in order to optimize and upgrade our infrastructure.
The impacted racks are : C1 → C22, D1 → D22, E1 → E21, F1 → F21

As a result servers will lose their public network connectivity as our router is being upgraded, but private network connectivity will still be functional.
Public network will be back online once the maintenance is completed.

If your server is in the said racks, you will receive a ticket on your account.

Start : 14th april, 2021 - 04.00 UTC (06.00 CEST)
Duration : 90 minutes
Posted Mar 24, 2021 - 11:02 CET
This scheduled maintenance affected: Dedibox - Datacenters (DC3).