[DC5] RPN router maintenance

Scheduled Maintenance Report for Scaleway

Completed

The scheduled maintenance has been completed.
Posted Oct 24, 2022 - 14:30 CEST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 24, 2022 - 14:00 CEST

Scheduled

Following hardware instabilities on a RPN distribution router in DC5 resulting in random reboots.
We are planning a hardware replacement today at 14:00 LT and customers should experience RPN unreachability during this operation window.

Start time : 14:00 LT
Ops duration : 30mn expected
Posted Oct 24, 2022 - 12:21 CEST
This scheduled maintenance affected: Dedibox - Datacenters (DC5) and Dedibox - Products (RPN).