Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 14, 2021 - 08:00 CEST
Scheduled
We will carry out the semi-annual preventive maintenance of CRAC units according to the schedule below. CRAC units will be shut down one at a time, so as not to impact the cooling of halls.
Each IT zone has CRAC unit called «backup»: each CRAC unit is doubled. Each MVLB hall has a main air hanling unit (AHU).
The maintenance will be done according to the following schedule: • MLVBs : 14/06/2021 to 18/06/2021 • Operators halls : 14/06/2021 and 18/06/2021 • IT halls n°4 : 17/06/2021 and18/06/2021 • IT halls n°3 : 16/06/2021 and17/06/2021 • IT halls n°2 : 14/06/2021 and15/06/2021 • IT halls n°1 : 14/06/2021 and15/06/2021
The maximum cut-off time per CRAC unit is otherwise defined at 1 hour.
As a result, we will experience a loss of cooling redundancy during the preventive maintenance operation of a CRAC unit (max 1h). No impact on the cooling of facilities.
Posted Apr 02, 2021 - 16:50 CEST
This scheduled maintenance affected: Dedibox - Datacenters (DC3).