[DC5] Firmware update of inverters
Scheduled Maintenance Report for Scaleway
Completed
The scheduled maintenance has been completed.
Posted Jan 20, 2022 - 17:00 CET
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 19, 2022 - 09:00 CET
Scheduled
We are going to carry out annual maintenance on the inverters of the electrical chains of TGBT 1.1 and 1.2 then 2.1 and 2.2 The inverters of these electrical chains supply the racks in computer rooms 1 and 2.

The operations will be carried out by our maintainer and under our permanent supervision, according to the following provisional schedule:
- Wednesday, January 19th: LT 7.1 and LT 7.2
- Thursday, January 20st: LT 2.1 and LT 2.2

Our teams as well as the usual maintenance companies will be mobilized for the perfect progress of operations. This intervention does not present any particular risk of service interruption and will be processed on worked hours.

In the event of an electrical cut in the HV network during the operation, the maintenance in progress will be interrupted to restart the UPS. The load will be powered by the batteries of the active inverter of the electric chain during the maintainer fallback. The generators will take over the electric charge automatically thereafter.
Posted Jan 14, 2022 - 15:24 CET
This scheduled maintenance affected: Dedibox - Datacenters (DC5).