[DC2][RPN] - RPN Switch Isolation Room 103 Rack F09

Scheduled Maintenance Report for Scaleway

Completed

The scheduled maintenance has been completed.
Posted Dec 03, 2025 - 09:00 CET

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Dec 03, 2025 - 08:00 CET

Scheduled

Due to new network flaps seen on RPN switch located on Room 103 Rack F09, we'll proceed with the change of port on the router on which is connected the switch.
Customer should expect RPN traffic impact the time of the intervention (should be around 30 minutes maximum)
Traffic to the internet is not impacted
Posted Nov 28, 2025 - 18:11 CET
This scheduled maintenance affected: Dedibox - Datacenters (DC2) and Dedibox - Products (RPN).