[PL-WAW-2] Electrical system redundancy maintenance

Scheduled Maintenance Report for Scaleway

Completed

The scheduled maintenance has been completed.
Posted 1 month ago. Mar 05, 2025 - 06:00 CET

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted 1 month ago. Mar 05, 2025 - 00:00 CET

Update

If you have any question feel free to contact our support team.
Posted 1 month ago. Mar 04, 2025 - 16:59 CET

Scheduled

We will be performing a maintenance on the electrical redundancy of our DC PL-WAW-2 overnight.

This will not impact your services nor create downtime.

However, you may notice a loss of electrical redundancy in your service monitoring. Power track A will be shut down on March 5, and power track B on March 6, 2025.

The schedule is as follows:

March 5, 2025
• 00:00 – Power shutdown for IT equipment on power track A
• 00:15 – 05:00 – Execution of works
• 05:00 – 06:00 – Power supply restored

March 6, 2025
• 00:00 – Power shutdown for IT equipment on power track B
• 00:15 – 05:00 – Execution of works
• 05:00 – 06:00 – Power supply restored
Posted 1 month ago. Mar 04, 2025 - 16:59 CET
This scheduled maintenance affected: Elements - AZ (pl-waw-2).