Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted 1 month ago. Mar 05, 2025 - 00:00 CET
Update
If you have any question feel free to contact our support team.
Posted 1 month ago. Mar 04, 2025 - 16:59 CET
Scheduled
We will be performing a maintenance on the electrical redundancy of our DC PL-WAW-2 overnight.
This will not impact your services nor create downtime.
However, you may notice a loss of electrical redundancy in your service monitoring. Power track A will be shut down on March 5, and power track B on March 6, 2025.
The schedule is as follows:
March 5, 2025 • 00:00 – Power shutdown for IT equipment on power track A • 00:15 – 05:00 – Execution of works • 05:00 – 06:00 – Power supply restored
March 6, 2025 • 00:00 – Power shutdown for IT equipment on power track B • 00:15 – 05:00 – Execution of works • 05:00 – 06:00 – Power supply restored
Posted 1 month ago. Mar 04, 2025 - 16:59 CET
This scheduled maintenance affected: Elements - AZ (pl-waw-2).