[DC2] Scheduled maintenance - Room : 202-B / Rack : H9
Scheduled Maintenance Report for Scaleway
Completed
After further verification we confirm that the scheduled maintenance has been completed with some delays. The timestamps are the following : 9h38 UTC+1 - 10h00 UTC+1. Our apologies for the delay.
Posted Jan 27, 2021 - 09:30 CET
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 27, 2021 - 09:01 CET
Scheduled
A scheduled maintenance is planned in Room : 202-B / Rack : H9 in DC2 in order to replace a faulty equipement.

As a result servers will be powered off during the operation and will be back on once it's over.

The status will be updated accordingly at the end of the maintenance for you to manage your server again.

Start :
January 27th, 2021 - 0800 UTC (0900 LT)

Duration :
30 minutes
Posted Jan 20, 2021 - 11:41 CET