[DC3] Preventive electrical maintenance of generators+ load tests of generators
Scheduled Maintenance Report for Scaleway
Completed
The scheduled maintenance has been completed.
Posted Aug 31, 2021 - 19:00 CEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 23, 2021 - 09:00 CEST
Scheduled
We’re going to realize the preventive electrical maintenance of generators.

The maintenance will be performed electrical chain by electrical chain, so that super-rescue generators (chain F1) can recover the load, in the event of an electrical incident coming from the usual network of energy supply.

Maintenance will be carried out according to the following forecast schedule :

- Chaine A : 16/08
- Chaine B : 17/08
- Chaine C : 18/08
- Chaine D : 19/08
- Chaine F1 : 24/08
- Chaine F2 : 23/08

Every evening, generators on which maintenance has been done will be put back into service and a generators off-load test will be performed. Load test of at least 30 minutes will be performed after each maintenance day. No generator will remain out of service in absence of the maintenance company.
Posted May 27, 2021 - 17:39 CEST