Status impact color legend
  • Black impact: None
  • Yellow impact: Minor
  • Red impact: Major
  • Blue impact: Maintenance

[DC3] Preventive electrical maintenance of generators+ load tests of generators

Scheduled Maintenance Report for Scaleway

Completed

The scheduled maintenance has been completed.
Posted Aug 31, 2021 - 19:00 CEST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 23, 2021 - 09:00 CEST

Scheduled

We’re going to realize the preventive electrical maintenance of generators.

The maintenance will be performed electrical chain by electrical chain, so that super-rescue generators (chain F1) can recover the load, in the event of an electrical incident coming from the usual network of energy supply.

Maintenance will be carried out according to the following forecast schedule :

- Chaine A : 16/08
- Chaine B : 17/08
- Chaine C : 18/08
- Chaine D : 19/08
- Chaine F1 : 24/08
- Chaine F2 : 23/08

Every evening, generators on which maintenance has been done will be put back into service and a generators off-load test will be performed. Load test of at least 30 minutes will be performed after each maintenance day. No generator will remain out of service in absence of the maintenance company.
Posted May 27, 2021 - 17:39 CEST
This scheduled maintenance affected: Dedibox - Datacenters (DC3).