[DC5] Scheduled maintenance on RPN router

Scheduled Maintenance Report for Scaleway

Completed

The scheduled maintenance has been completed.

We have detected that the new replacement wasn't working and will try again at 1PM UTC (2PM ETC). Still no impact to be expected.
Posted Feb 15, 2021 - 12:01 CET

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 15, 2021 - 11:30 CET

Scheduled

A scheduled maintenance is planned on a RPN router in DC5 to perform hardware replacement. This router feeds RPN to racks D1 to D19 and racks C1 to C6.

No impact to be planned with the RPN during the operation.

Updates will be posted below as the maintenance is going on.

Start : February 15th, 2021 - 10:30 UTC - 11:30CET

Duration : 30 minutes
Posted Feb 11, 2021 - 15:03 CET
This scheduled maintenance affected: Dedibox - Datacenters (DC5).