[DC3] Scheduled maintenance - Pump box

Scheduled Maintenance Report for Scaleway

Completed

The scheduled maintenance has been completed.
Posted Jan 26, 2021 - 17:30 CET

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 26, 2021 - 10:00 CET

Scheduled

We will do the curative maintenance of the pumps unit of chillers 5.
The 2020 thermography report shows a tightening fault on a circuit breaker.
Operations will be performed by our maintainer.

Since only one refrigeration unit is switched off at the same time, only the redundancy is degraded.

In the event of a failure of a chiller operating in the same substation as the maintenance one, our maintainer will have the possibility to restart the chiller quickly or, in case of failure, to mix the chilled water networks SSA and SSB.

Impact :
None expected.

Start :
January 26th, 2021 : 0900 UTC (1000 LT)

Duration :
7 hours 30 minutes
Posted Jan 20, 2021 - 11:37 CET