[DC5] Switching off the TGBT 8.2 (Main Switchboard) for the installation of a new power cable
Scheduled Maintenance Report for Scaleway
Completed
The scheduled maintenance has been completed.
Posted Feb 08, 2023 - 12:00 CET
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 08, 2023 - 08:01 CET
Scheduled
As part of our thermographic checks, we identified abnormal overheating of a connection between the UPS bypass and the TGHQ.

In order to resolve this anomaly, we are going to replace this connection.

This requires the powering down of the technical room 8.2 and will impact one of the electrical supply of the racks in room 7 and 8.

The equipment will be powered by a single power feed for the duration of the intervention, from 8:00 a.m. to 12:00 p.m. on 23/02/08.

In the event of an Utility power loss during this period, the second power feed will remain powered since it is UPS and generator backed up.

The risk is mainly on the power supply of the equipment in production at the rack level
Posted Jan 20, 2023 - 10:45 CET
This scheduled maintenance affected: Dedibox - Datacenters (DC5).