[DEDIBOX]-FR-PAR-1 - Room 103 Rack F09 - RPN Switch Isolation

Scheduled Maintenance Report for Scaleway

Completed

The scheduled maintenance has been completed.
Posted Sep 24, 2025 - 09:00 CEST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 24, 2025 - 08:30 CEST

Scheduled

Due to network flaps seen on RPN switch located on Room 103 Rack F09, we'll proceed with the replacement of the optic on this specific switch uplink.

Customer should expect RPN traffic impact the time of the intervention (should be less than 5 minutes)

Traffic to the internet is not impacted

Scheduled Start : 24th of September at 8:30AM (local-time)
Scheduled End : 24th of September at 9:00AM (local-time)
Posted Sep 22, 2025 - 10:58 CEST
This scheduled maintenance affected: Dedibox - Datacenters (DC2) and Dedibox - Products (RPN).