[DC5] Fire extinguishing installation work from 19/01 to 27/01
Scheduled Maintenance Report for Scaleway
Completed
The scheduled maintenance has been completed.
Posted Jan 19, 2023 - 09:00 CET
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 19, 2023 - 08:00 CET
Scheduled
We are going to work in your computer room 7 to install water mist fire extinguishing pipes (installation of stainless steel
tubes without cutting in the room).
The work will take place in the computer room 7 as well as in the technical shaft (above the datahall).
The workers will be accompanied by Scaleway staff during the work near your equipment in order to avoid any incident.
Therefore, no impact on your equipment is expected.
Posted Jan 06, 2023 - 09:52 CET
This scheduled maintenance affected: Elements - AZ (fr-par-2).