[DC5] Modification of the electrical connection of a rack in production - Room 7/D

Scheduled Maintenance Report for Scaleway

Completed

The scheduled maintenance has been completed.
Posted Sep 09, 2022 - 09:00 CEST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 05, 2022 - 09:00 CEST

Update

We will be undergoing scheduled maintenance during this time.
Posted Aug 25, 2022 - 14:59 CEST

Scheduled

Following the commissioning of a new bar duct, a migration of one of the two electrical channels is required on the servers in production in room 7.

Impact: Each rack listed below will be powered by a single channel for approximately 1⁄2 hour per rack.
Room 7 - Bay D1 to D15 - 05/09/2022
Room 7 - Bay D16 to D30 - 06/09/2022
Room 7 - Bay D31 to D45 - 07/09/2022
Room 7 - Bay D46 to D60 - 08/09/2022
Room 7 - Bay D61 to D73 - 09/09/2022
Posted Aug 25, 2022 - 14:48 CEST
This scheduled maintenance affected: Dedibox - Datacenters (DC5).