Status impact color legend
  • Black impact: None
  • Yellow impact: Minor
  • Red impact: Major
  • Blue impact: Maintenance

[DC2] Emergency switch maintenance room 202A rack A5

Scheduled Maintenance Report for Scaleway

Completed

The scheduled maintenance has been completed.
Posted Nov 03, 2021 - 10:20 CET

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Nov 03, 2021 - 09:30 CET

Scheduled

Our network team has to perform an emergency maintenance on switch room 202A rack A5, servers in this rack will be unavailable for about 5 minutes within a time period of 1 hour, between 08:30 and 09:30 UTC.

In case a hardware issue occurs, the switch will have to be replaced and therefore cause a longer downtime than expected. Should such an issue arise, we will update this maintenance status to let you know.
Posted Nov 02, 2021 - 17:40 CET
This scheduled maintenance affected: Dedibox - Products (Dedibox) and Dedibox - Datacenters (DC2).