[DC5] Room 2 and 7 CTA shutdown operating tests

Scheduled Maintenance Report for Scaleway

Completed

The scheduled maintenance has been completed.
Posted Apr 20, 2022 - 17:00 CEST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 20, 2022 - 14:00 CEST

Scheduled

As part of the preventive maintenance operations of the Datacenter, we will carry out fire detection tests.
During this maintenance and testing, the AHUs in rooms 2 and 7 will be shut down one after the other.
Once our test has been validated, the CTAs will be put back into operation. No impact on room temperatures are expected.
This maintenance will be supervised by our service provider and internally by the BETID Scaleway.
Posted Apr 12, 2022 - 11:17 CEST