Status impact color legend
  • Black impact: None
  • Yellow impact: Minor
  • Red impact: Major
  • Blue impact: Maintenance

[VPC] [FR-PAR] VPC Edge routers fix deployment in FR-PAR

Scheduled Maintenance Report for Scaleway

Completed

The scheduled maintenance has been completed.
Posted Dec 09, 2025 - 13:01 CET

Update

fr-par-1 Edge routers are now patched, we are taking some time to monitor everything then we will proceed with the next 2 availability zones one by one
Posted Dec 09, 2025 - 11:52 CET

Update

A DNS/DHCP server failed to start properly during an edge restart sequence, this caused a brief interruption on these services and should be fixed now.
Posted Dec 09, 2025 - 11:43 CET

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Dec 09, 2025 - 10:00 CET

Scheduled

From Tuesday morning at 10:00 CET, we will deploy the fix related to last week's incident.
We expect only a few perturbations to occur while we process all VPC Edge routers in the FR-PAR region.
The maintenance is expected to last a few hours to patch all VPC Edge routers in all FR-PAR availability zones.
Posted Dec 05, 2025 - 17:00 CET
This scheduled maintenance affected: Elements - AZ (fr-par-1, fr-par-2, fr-par-3) and Elements - Products (Edge service).