[DC5] Preventive maintenance of 48V UPS in operator room
Scheduled Maintenance Report for Scaleway
Completed
The scheduled maintenance has been completed.
Posted Jul 13, 2021 - 17:00 CEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 12, 2021 - 09:00 CEST
Scheduled
We will be performing the preventive maintenance of the 48V UPSes in the operator room.
The maintenance will be carried out according to the following schedule:
- UPS A: 12/07 from 09:00 CEST to 17:00 CEST
- UPS B: 13/07 from 09:00 CEST to 17:00 CEST

Impact: Electrical redundancy degradation, no impact is expected on services.
Posted Jun 24, 2021 - 13:55 CEST
This scheduled maintenance affected: Dedibox - Datacenters (DC5).