[NETWORK] Public Gateways: changing the Public IP behavior from a NAT IP to a Routed IP.

Scheduled Maintenance Report for Scaleway

Completed

The scheduled maintenance has been completed.
Posted May 31, 2024 - 08:00 CEST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted May 27, 2024 - 08:00 CEST

Scheduled

As a reminder of the email sent on April 3rd, 2024 to Public Gateways users, we are changing the Public IP behavior from a NAT IP to a Routed IP.

In order to be compatible with IP Mobility, you should upgrade your Public Gateway.

There are two ways to do this:

1. Manually, at your convenience, through the Console. The consequence will be a short downtime of your Public Gateway for a maximum of 1 minute.

2. Or automatically, during the forced upgrade between May 27th, 2024, and May 31st, 2024. This will involve deleting your current Public Gateway and spawning a new one with the same configuration, compatible with IP Mobility.

Questions? Need help? Do not hesitate to open a ticket or ask on the #public-gateway Slack channel.
The Network Team.

P.S: If you have already upgraded your Public Gateway, you are all set. Please disregard the above message.
Posted May 14, 2024 - 10:40 CEST
This scheduled maintenance affected: Elements - Products (Network).